Transportation of the repaired 100 t stator back to Devin HPP
In order to carry out the transportation of the 100 t stator with a diameter of 5.5 metres from CERB to Devin Hydro Power Plant we engaged the Traffic Police Department, the National Road Infrastructure Agency (NRIA), escort vehicles and a specialised hauler platform for oversized cargo. During the transport operation we took all measures to ensure the safety of the other road users, including temporary blocking the road section between Krichim and Devin. Prior to the day of the transportation the bridge leading to the power plant was inspected and the crossing was additionally secured using uniformly distributed loading in front of and behind the hauler.